01-16-2026 03:16 AM
Hi, I have a job where a job cluster is reused twice for task A and task C. Between A and C, task B runs for 4 hours on a different interactive cluster. The issue here is that the job cluster doesn't terminate as soon as Task A is completed and sits idle for 4 hrs. Is this expected behaviour when reusing a job cluster? Do we need to make sure that job cluster is reused only for consecutive tasks?
TASK A -> TASK B -> TASK C
More on job cluster reuse:
https://community.databricks.com/t5/technical-blog/maximizing-resource-utilisation-with-cluster-reu…