10-08-2024 12:54 AM
I know this post was a while ago, but I've hit this issue, and come up with using if/else conditions between the tasks with a Job parameter of "IsActiveTask2" with a True or False, and then I can have the Task2 dependant on the success of this conditional step being True. I hope that makes sense?